Q. 111: Which type of graph the image in the following exhibit represent?
Exhibit



A. Merged graph
B. Drill down graph
C. Cross scenario graph
D. Auto correlated graph 

<<<<<< =================== >>>>>>

Q. 112: Which scenario run verifies that parameterized data works under concurrent usage?
A. Debug
B. Full load
C. Top time
D. Scalability

<<<<<< =================== >>>>>>
Q. 113: Which does the image shown in the following exhibit represent?

Exhibit




A. Thumbnail 
B. Extended Log
C. Content check
D. Snapshot on error

<<<<<< =================== >>>>>>
Q. 114: Which description describes the schedule shown in the following exhibit?
Exhibit





A. The scenario is scheduled by scenario, consisting of two groups: one group with 10 Vusers, the other group with 15 Vusers, the duration action is set for 5 minutes.

B. The scenario is scheduled by group, consisting of two groups: one group with 10 Vusers, the other group with 15 Vusers, each group has the ramp up is set to 1 Vusers every 5 seconds.
C. The scenario is scheduled by group, consisting of two groups: one group with 10 Vusers, the other group with 15 Vusers. Each group has the duration action scheduled for 5 minutes.
D. The scenario is scheduled by scenario, consisting of one group: the ramp up is set to 2 Vusers every 20 seconds. The duration is set to 5 minutes and ramp down is set to 5 Vusers every 30 seconds.
<<<<<< =================== >>>>>>
Q. 115: You are running a 10% load test. The following exhibit shows a list of business processes, the desired number of business processes per hour, and the number of translations per business process. How many transactions should complete during the one hour full load test?
Exhibit






A. 2,000
B. 20,000
C. 5,000
D. 380,000

<<<<<< =================== >>>>>>
Q. 116: Which statement is true about the availability of VuGen?
A. VuGen is only included when performing a full installation.
B. An extra license is required to obtain VuGen.
C. VuGen is available in a full installation, but is only activated if QuickTest Professional is also installed.
D. VuGen is available in a full installation and as a standalone installation.

<<<<<< =================== >>>>>>
Q. 117: Which features are provided by WAN Emulation? (Select two.)
A. Simulate network latency between Load Generators and tested machines
B. Measure network bandwidth utilization of HP LoadRunner hosts during tests
C. Measure response time of a transaction during performance tests
D. Define maximum bandwidth of a Load Generator 

E. monitor uptime of a Load Generator
<<<<<< =================== >>>>>>
Q. 118: During a test run, why is it important to insert Run-time Monitors on Controller and Load Generator machines?
A. To verify that Vuser ramp and Load Generator CPU usage are approximately the same
B. To verify that your test architecture is properly isolated from external disturbance
C. To ensure that test architecture performance is not lower than that of the architecture under test
D. To ensure that your test architecture can generate the desired load without itself becoming a bottleneck

<<<<<< =================== >>>>>>
Q. 119: Which goal is an example of a measurable goal?
A. The number of iterations defined in the Run-time Settings (RTS)
B. The identification of the name of the application server
C. The expected transaction response time
D. The number of Load Generators to be used

<<<<<< =================== >>>>>>
Q. 120: Which goal is an example of a high level goal?
A. Error rate may not be higher than 10% of all transactions.
B. Update transaction must work in peak time.
C. 500 users must be able to log in at the same time.
D. The Search transaction may not take longer than 3 seconds.



Correct Answers to Earlier Questions - Q.111 to Q 120 are as under:

Question No.Correct Answer
Q. 111C
Q. 112A
Q. 113D
Q. 114C
Q. 115C
Q. 116D
Q. 117A,D
Q. 118D
Q. 119C
Q. 120B